In SAP PP Planning, which of the following strategy do not allow and not expected of you to create Planned Independent Requirement ?
(only one answers)
A) 11.
B) 30.
C) 20.
D) 50.
E) 70.
.
(only one answers)
A) 11.
B) 30.
C) 20.
D) 50.
E) 70.
.
A, B) Both Strategy 11 and 30 are Make-to-Stock Strategies where PIR are possible.
ReplyDeleteD) Strategy 50 is Planning without Final Assembly where PIR is allowed so that planning for the Assemblies and Components can take place before the Sales Order for the Finished Goods arrive.
ReplyDeleteE) Strategy 70 is Make-to-Stock Strategy for Planning at the Assembly Level where PIR is created at the Assembly.