In SAP MRP, which of the following MRP Type will never create dependent requirements for the child component ?

(only one answer)

A)   PD.
B)   M1.
C)   VB.
D)   M0.
E)   P1.
.

2 comments:

  1. PD, P1, P2, P3, P4 are MRP types for PP MRP
    M0, M1, M2, M3, M4 are MRP types for PP MPS
    VB is for MM Consumption Based Planning Re-Order Point.