In SAP PP (ECC6 EhP6), which of the following time elements can be included in the Reduction Strategy during scheduling ?
(A) Setup time.
(B) Teardown time.
(C) Queue time.
(D) Wait time.
(E) Move time.
.
(A) Setup time.
(B) Teardown time.
(C) Queue time.
(D) Wait time.
(E) Move time.
.
Answer: C, E
ReplyDeleteReduction Strategy via the following:
ReplyDelete. Queue time
. Move time
. Order Splitting/Overlap
. Reduce Float times