In SAP MRP, to avoid re-scheduling messages due to small changes of dates in demand supply; you can set a tolerance forward or backward using the MRP Group. The tolerance check is valid for the following MRP elements except which one ?
(only one answer)
A) Planned Orders.
B) Firmed Planned Orders.
C) Purchase Orders.
D) Production Orders.
E) Manually created Purchase Requisitions.
.
(only one answer)
A) Planned Orders.
B) Firmed Planned Orders.
C) Purchase Orders.
D) Production Orders.
E) Manually created Purchase Requisitions.
.
Answer: A
ReplyDeletePlanned Orders are not considered for tolerance checks of this case.