Question no 2593 : Re-schedule tolerance

In SAP MRP, to avoid re-scheduling messages due to small changes of dates in demand supply; you can set a tolerance forward or backward using the MRP Group. The tolerance check is valid for the following MRP elements except which one ?

(only one answer)

A)    Planned Orders.
B)    Firmed Planned Orders.
C)    Purchase Orders.
D)    Production Orders.
E)    Manually created Purchase Requisitions.
.