As at ECC6.0 EhP6, to set up Order Change Management (OCM), you would have to assign an ________________________ .
(only one answer)
A) Overall Profile to the Work Scheduling view in the Material Master.
B) Overall Profile to the MRP3 view in the Material Master.
C) Overall Profile to the Plant dependent Production Order type in the Configuration.
D) Overall Profile to the Plant independent Production Order type in the Configuration.
E) Overall Profile to the Production Scheduler in the Configuration.
.
(only one answer)
A) Overall Profile to the Work Scheduling view in the Material Master.
B) Overall Profile to the MRP3 view in the Material Master.
C) Overall Profile to the Plant dependent Production Order type in the Configuration.
D) Overall Profile to the Plant independent Production Order type in the Configuration.
E) Overall Profile to the Production Scheduler in the Configuration.
.
Answer: A
ReplyDeleteThis Overall profile should be configured in SPRO > Production > Shop Floor Control > Operations > Change Management for Production Orders > Define Overall Change Profile. There are 3 Change Profile in the Overall Profile (Control for Changes in Sales Order, Master Data changes, and Assembly Order changes). The Overall Profile is then to be assigned to the Material Master in the Work Scheduling view at the Plant level.
ReplyDelete