Question no 2615 : Rounding Profile Calculation 4

In SAP MRP, with Rounding Profile and lot size fine tuning data according to the S/R List below, inspect carefully the screen data and deduce MRP run results ?


(only one answer)

A)  2 Planned Orders of 2000 each and 1 Planned Order of 1500.
B)  3 Planned Orders of 2000 each.
C)  3 Planned Orders of 1500 each and 1 Planned Order of 800.
D)  4 Planned Orders of 1500 each.
E)  1 Planned Order of 5500.
.

2 comments:

  1. As the initial net requirement was 5280. It falls in the threshold of 900 with a rounding of 1000.
    Since the max lot size is 2000, the system would create 2 planned Orders of 2000 each.
    With a balance of 1280 to be fulfilled, the system cannot issue a Planned Order of 1000 even if it falls on the threshold of 900 with a rounding of 1000; this is due to minimum lot size of 1500.
    In this case we expect the supplier to send 1 box of 1000 and 5 box of 100 to fulfill the remaining quantity.
    Therefore, MRP result:
    2 planned order of 2000 each (due to the maximum lot size) 4 boxes of 1000
    1 planned order of 1500 each (due to the minimum lot size) 1 box of 1000 and 5 boxes of 100