Question no 2622 : Interoperation time



Determine which of the following are included in the Inter-operation time ? 

(more than one answers) 

A)   Move time.
B)   Queue time. 
C)   Wait time. 
D)   Float before production.
E)   Float after production. 
.


1 comment:

  1. Inter-operation time includes the following:
    . Move time
    . Queue time
    . Wait time
    . Float before production
    . Float after production
    . Planned delivery time (from an operation externally processed)