Question no 2596 : Activating MRP Run

In SAP MRP, which of the following are per-requisites of an MRP run for a Mateiral in a Plant ?

(more than one answers)

A)  MRP activated at the Plant level in the Customizing.
B)  MRP area activated at the Plant level in the Customizing.
C)  A Vaild MRP Type in the MRP 1 data view in the Material Master.
D)  MRP Plant parameter was created.
E)  A valid Availability Check Group in the MRP 3 data view in the Material Master.
.

2 comments:

  1. B) MRP Area activation is not necessary to perform MRP run at the Plant level.

    ReplyDelete
  2. E) AV Check Group in the MRP 3 data view is not required for MRP run.

    ReplyDelete