SAP CA96 Update Material Master with Scheduling Results, in SAP PP ECC6.0 EhP5, which of the following are not one of the possible updates ?
(only one answer)
A) Interoperation time.
B) Setup time.
C) Processing time.
D) Assembly scrap factor.
E) Operation scrap factor.
.
(only one answer)
A) Interoperation time.
B) Setup time.
C) Processing time.
D) Assembly scrap factor.
E) Operation scrap factor.
.
Answer: D
ReplyDeleteCheck out transaction CA96 to see what it does !
ReplyDelete