In SAP PP Planning, a Strategy Group is _____________________ ?
(more than one answers)
A) Contains only one main strategy and one sub-strategy.
B) Contains only one main strategy and one or more sub-strategy.
C) May contain only one main strategy and no sub-strategies.
D) Can be assigned to Material Master or MRP Group.
E) Can be assigned to Material Master or MRP Controller.
.
(more than one answers)
A) Contains only one main strategy and one sub-strategy.
B) Contains only one main strategy and one or more sub-strategy.
C) May contain only one main strategy and no sub-strategies.
D) Can be assigned to Material Master or MRP Group.
E) Can be assigned to Material Master or MRP Controller.
.
Answer: B, C, D
ReplyDeleteA, B, C) In the Configuration, the minimum configuration of a Strategy Group is one Main Strategy. However, it may also contain one or more sub-strategies.
ReplyDeleteD, E) In the IMG, you can find within the MRP Group Parameter, where the Strategy Group is assigned.