Question no 3193 : Source List Requirement

In SAP MM as at ECC6.0 EhP7, Source List Requirement can be set at the which of the following ?

(more than one answers)

A)   MRP Group Parameter.
B)   Plant Parameter.
C)   Purchasing Document Type.
D)   Material Master Purchasing Data view.
E)   Approved Vendor List.

2 comments:

  1. B) This is done at the IMG (customizing), you can find it in the Purchasing folder, when you decide to set the Source List Requirement at the Plant level. All materials created for that Plant must have a Source List for Procurement process.

    ReplyDelete
  2. D) Setting the Source List Requirement in the Material Master Purchasing Data view will make it material dependent.