Question no 3191 : Read PP Master Data

In SAP PP as at ECC6.0 EhP6, the "Read PP Master Data" function cannot be Executed when ....

(more than one answers)

A)   Production Order has been Released.
B)   Production Order has been Technically Completed.
C)   Operation has been confirmed.
D)   Goods Movement has been carried out.
E)   Shop Paper has been Printed.
.

1 comment:

  1. As long as the Order is Released and no execution task has been activated like Confirmation, Backflush, Goods Issue, you can Read PP Master Data. (that was the last test).