Question no 3192 : MRP Generating Delivery Schedule

In SAP MM or PP as at ECC6.0 EhP7, the pre-requisite for generating Delivery Schedules in an MRP run are which of the following ?

(more than one answers)

A)   Contract.
B)   Quota Arrangement.
C)   Source List.
D)   Purchasing Info Record.
E)   Scheduling Agreement.

1 comment:

  1. I could have registered C and E as the answer.
    First, Delivery Schedules are the characteristics of a Scheduling Agreement (E), in order for MRP run to genreate it automatically, you have to set an MRP relevancy indicator in the Source List.
    ...
    Now the Purchasing Info Record is a little tricky, usually it is a norm to create the PIR as a pre-requisite to the Source List or generate the PIR when saving the Scheduling Agreement.