Question no 3168 : Response Profile in SAP PM Notification

In SAP Plant Maintenance as at ECC6.0 EhP6, in the configuration; you assign the Response Profile and the Service Profile with the Service Window to the Maintenance Notification in the customizing for which of the following purpose ?

(only one answer)

A)   Determine the Task for the Notification.
B)   Determine the Priority end date for the Notification.
C)   Determine the Activity for the Notification.
D)   Determine the Service level for the Notification.
E)   Determine the Task List to be assigned to the Notification.

2 comments:

  1. This feature allows you to set Automatic Task determination indicator in the Maintenance Plan for Notification as call objects so that when maintenance is due, the Notification called will be assigned automatically with the right Task.

    ReplyDelete