In SAP MM as at ECC6.0 EhP7, which of the following need not be created at the Plant level ?

(more than one answers)

A)   Source List.
B)   Quota Arrangement.
C)   Purchasing Info Record.
D)   Contract.
E)   Scheduling Agreement.
.

2 comments:

  1. C) An option to create the PIR with or without Plant, and this is in accordance to Purchasing Negotiation strategy (PIR without Plant means an ability to negotiate one price for all plants by a Purchasing Organization)

    ReplyDelete
  2. D) Central Contract without Plant usually negotiates a Total quantity with a base price for several plants, subsequently purchase orders called "Released Orders" will be created with reference to the Contract for each Plant.