In SAP PP as at ECC6.0 EhP7, which of the following time elements make up the Inter-operation times ?
(more than one answers)
A) Queue time.
B) Setup time.
C) Processing time.
D) Wait time.
E) Move time.
.
(more than one answers)
A) Queue time.
B) Setup time.
C) Processing time.
D) Wait time.
E) Move time.
.
Answer: A, D, E
ReplyDeleteQueue time + Wait time + Move time = Inter-Operation time