This Blog is mainly on SAP Exam Questions and Selected "How-to" SAP processes

Wednesday, June 22, 2016

Question no 3189 : Inspection Point in QM

In SAP QM as at ECC6.0 EhP7, the Inspection Point can be assigned to the following EXCEPT ?

(more than one answers)

A)    Material Master Inspection Type detail.
B)    Material Specification header.
C)    Inspection Plan Header.
D)    Maintenance Task List Header.
E)    Routing Header.
.

2 comments:

  1. You can assign the Inspection Point to the following:
    . Inspection Plan Header
    . Routing header
    . Rate Routing header
    . Recipe header
    . Maintenance Task List Header

    ReplyDelete

Note: Only a member of this blog may post a comment.