Question no 3167 : Maintenance Planning for External Services Calls

In SAP ECC6.0 EhP6, which of the following are mandatory requirements when setting up a Maintenance Plant for External Services Calls ?

(more than one answers)

A)   General Ledger Account for Expenses posting.
B)   Settlement Rules.
C)   Settlement Order.
D)   Framework Purchase Order.
E)   Technical Object.
.

2 comments:

  1. The following should be entered in an MP for external services calls:
    . G/L for the P&L expenses (when approve service entry sheet will post to this)
    . Settlement Order (for cost debit when approve service entry sheet)
    . Framework PO
    . Service Master (optional)

    Unfortunately, SAP has yet to allow EQ or FL in the MP. (however, you can reflect the EQ or FL in the Settlment Order assigned to the MP)