In SAP PM as at ECC6.0 EhP6, consider the following requirement

"A customer wants a Preventive Maintenance Plan for executing the company vehicles for plan due either every 3 months or 5000 km", the job is to be executed by an external vendor".

which of the following type of Maintenance Plan is most appropriate.

(only one answer)

A)   Single-Cyle Plan
B)   Strategy Plan.
C)   Multi-Counter Plan.
D)   External Procurement Maintenance Plan.