In SAP PM as at ECC6.0 EhP6, consider the following requirement
"A customer wants a Preventive Maintenance Plan for executing the company vehicles for plan due either every 3 months or 5000 km", the job is to be executed by an external vendor".
which of the following type of Maintenance Plan is most appropriate.
(only one answer)
A) Single-Cyle Plan
B) Strategy Plan.
C) Multi-Counter Plan.
D) External Procurement Maintenance Plan.
E) Multi-Characteristics Plan.
.
"A customer wants a Preventive Maintenance Plan for executing the company vehicles for plan due either every 3 months or 5000 km", the job is to be executed by an external vendor".
which of the following type of Maintenance Plan is most appropriate.
(only one answer)
A) Single-Cyle Plan
B) Strategy Plan.
C) Multi-Counter Plan.
D) External Procurement Maintenance Plan.
E) Multi-Characteristics Plan.
.
Answer: C
ReplyDeleteOnly Multi-Counter Plan supports more than one UOM for MP Planning.
ReplyDelete