In SAP PM as at ECC6.0. EhP6, the Strategy Group can be assigned to which of the following ?
(more than one answers)
A) Plant Parameter.
B) MRP Controller.
C) MRP Group.
D) Material Master MRP3 data view.
E) MRP Type.
.
(more than one answers)
A) Plant Parameter.
B) MRP Controller.
C) MRP Group.
D) Material Master MRP3 data view.
E) MRP Type.
.
Answer: C, D
ReplyDeleteThe Strategy Group assigned to the Material Master's MRP3 3 view will be higher priority, else the system will use the MRP Group's Strategy Group and the MRP Group is assigned in the MRP 1 view. Both the Strategy Group and MRP Group is defined in the IMG.