In SAP MM or PP as at ECC6.0 EhP6, which of the following can be generated via a MRP run ?
(more than one answers)
A) Planned Orders.
B) Purchase Requisitions.
C) Purchase Orders.
D) Delivery Schedule for Purchase Orders.
E) Delivery Schedule for Scheduling Agreements.
.
(more than one answers)
A) Planned Orders.
B) Purchase Requisitions.
C) Purchase Orders.
D) Delivery Schedule for Purchase Orders.
E) Delivery Schedule for Scheduling Agreements.
.
Answer: A, B, E
ReplyDeleteMRP run can only generate the following:
ReplyDelete. Planned Orders
. Purchase Requisitions
. Schedule line for Scheduling Agreements