In SAP PM/CS, when a PM/CS Order is Released, __________________________________ . (as at ECC6.0 EhP6)
(more than one answers)
A) Goods movement can take place.
B) User status no longer is active.
C) Additional material and operations can no longer be added.
D) Purchase Requisitions are created.
E) Reservations are created.
.
(more than one answers)
A) Goods movement can take place.
B) User status no longer is active.
C) Additional material and operations can no longer be added.
D) Purchase Requisitions are created.
E) Reservations are created.
.
Answer: A, D
ReplyDeleteB) User status are functional until TECO.
ReplyDeleteD) 3 scenario possible (via Order-Plant dependent configuration)
ReplyDelete. Immediately (at created status)
. On release of Order
. Never
E) Reservations are always created immediately as the materials are added to the MO, regardless of created or released status (at least true as at ECC6.0 EhP6)