Question no 2824 : MRP Group and Plant Parameter

In SAP MM/PP ECC6.0 EhP6, which of the following parameters in the MRP Group parameter is also available in the Plant parameters ?


(more than one answers)

A)  Strategy Group.
B)  Consumption/Adjustment Horizon.
C)  Planning Horizon.
D)  Planning Time Fence.
E)  BOM Explosion.
.

2 comments:

  1. E) Both OPPQ (Plant Parameter) and OPPR (MRP Group Parameter) contains parameter of 'BOM Explosion Control'. since it it more than one answers and A, B, D is definitely not the answers as there don't exist in the Plant Parameter, I choose E as well.

    Even the 'BOM Explosion Control' feature is in both but the actual parameters are not similar
    OPPQ (Plant Parameter)
    . Explosion date
    . Exclude Bulk material (an indicator)
    . Sales/WBS Bom active
    . BOM Explosion no for MTO Production

    OPPR (MRP Group Parameter) has lesser parameter
    . Explosion date (similar to OPPR but with extra 'dependent on Plant Parameter')
    . Exclude Bulk Material but with extra 'dependnent on Plant Parameter)

    Therefore, you have to becareful when considering parameters which seems similar from the 'push button description' of OPPQ and OPPR but the content of the parameters may differ.