Question no 2827 : Source List creation

In SAP MM/PP ECC6.0 EhP6, to setup the Source List with the MRP Relevancy Indicator as show, what are per-requisites ?



(more than one answers)

A)   Material Master must have a Purchasing Data view.
B)   Source List requirement indicator is active in the Material Master Purchasing Data view.
C)   Source List requirement indicator is active in the Plant configuration in IMG.
D)   Purchasing Info Record is active for the Material/Vendor combination for the P.Org and Plant.
E)   Purchasing Info Record is active for the Material/Vendor combination for the P.Org without Plant.
.


4 comments:

  1. A) Purchasing view is required when creation the Source List, which means you cannot access the Source list without it.

    ReplyDelete
  2. B, C) Source List requirements is to ensure source are included in the Source list as per-requisite to procurement but without the settings, the source list can also be created.

    ReplyDelete
  3. D, E) PIR with or without Plant (but must be with Material and not Material Group) are considered valid when creating a Source List for the Material/Vendor/Pur.Org combination.

    ReplyDelete