In SAP PM ECC6.0 EhP6, setting up for internal Refurbishments are which of the following ?
(more than one answers)
A) Equipment must be linked to Material Master.
B) An Order type must be configured for reburbishment.
C) Material Master is expected to have split valuation setup.
D) Only Equipment Refurbishment is possible and not Functional Location.
E) Equipment must have been dismantled from superior Functional Location or superior Equipment and return to the warehouse.
.
(more than one answers)
A) Equipment must be linked to Material Master.
B) An Order type must be configured for reburbishment.
C) Material Master is expected to have split valuation setup.
D) Only Equipment Refurbishment is possible and not Functional Location.
E) Equipment must have been dismantled from superior Functional Location or superior Equipment and return to the warehouse.
.
D) Since Functional Location cannot be inventorized (link to Material/Serial), it cannot be subjected to the Refurbishment process.
ReplyDeleteBeware external refurbishment scenario uses PM01 Order Type and therefore answer B) is not true for external refurbishment scenario.