In SAP MM ECC6.0 EhP6, review the following configuration and select the correct answer ?


(more than one answers)

A)  This configuration is define at system installation and cannot be revoked.
B)  The result is the Accounting data view of the Material Master will be at the Company Code level.
C)  Valuation area will be equal to the Plant.
D)  Costing is no longer possible for the installed client.
E)  The result is the Accounting data view of the Material Master will be at the Plant level.
.

1 comment:

  1. The decision you make is valid for the whole client. Once set, it is not possible to switch the valuation level from plant to company code, or vice versa.

    It is recommended to set valuation at plant level when product costing and PP will be implemented.