In SAP Plant Maintenance as at ECC6.0 EhP6, which of the following Preventive Maintenance Plan scenario requires a Maintenance Strategy ?
(more than one answers)
A) Single-Cycle, time-based.
B) Time-based Strategy plan.
C) Single-Cycle, performance-based.
D) Performance-based Strategy plan.
E) Multi-Counter plan.
.
(more than one answers)
A) Single-Cycle, time-based.
B) Time-based Strategy plan.
C) Single-Cycle, performance-based.
D) Performance-based Strategy plan.
E) Multi-Counter plan.
.
Answer: B, D
ReplyDeleteA, C) Single-cylce plans do not required strategies.
ReplyDeleteE) Multi-counter plans uses Cycle-Sets instead of strategies.