In SAP MM ECC6.0 EhP6, when structuring a Plant. ___________________________ EXCEPT.
(only one answer)
A) A Plant need not have Storage Location for Procurement process.
B) A Plant must be assigned to a Company Code to complete a Procurement process.
C) A Plant can be assigned to exactly one Standard Purchasing Organization.
D) A Plant can be assigned to one or more Purchaaing Organizations.
E) A Plant must have at least one Purchasing Organization.
.
(only one answer)
A) A Plant need not have Storage Location for Procurement process.
B) A Plant must be assigned to a Company Code to complete a Procurement process.
C) A Plant can be assigned to exactly one Standard Purchasing Organization.
D) A Plant can be assigned to one or more Purchaaing Organizations.
E) A Plant must have at least one Purchasing Organization.
.
Answer: E
ReplyDeletePurchaaing Organization is not necessary for a Plant if no procurement is rewuired for the Plant. A plant can be a Production Plant only where stocks are directly reserved from another plant.