In SAP PM ECC6.0 EhP6, when reversal from Business Closing for a Maintenance Order, which of the following are correct ?
(more than one answers)
A) You can now perform receiving of non-stock Purchase Orders.
B) Invoice entry of non-stock Purchase Order can now takes place.
C) Purchase Requisition now re-open from deletion flag for further processing.
D) Settlement parameters are re-determined.
E) Settlement rule can be changed.
.
(more than one answers)
A) You can now perform receiving of non-stock Purchase Orders.
B) Invoice entry of non-stock Purchase Order can now takes place.
C) Purchase Requisition now re-open from deletion flag for further processing.
D) Settlement parameters are re-determined.
E) Settlement rule can be changed.
.
Answer: B, E
ReplyDeleteFrom CLSD to TECO (one step reverse)
ReplyDelete. Associated document such as PR, PO are not affected.
. Invoice entry for non-stock PO can still affect the MO as it is now in TECO status.
. Overhead Calculation and Settlement now possible (at TECO)
. Settlement rule can now be changed but it does not redetermine (re-determination of settlement rule is when TECO to REL)