In SAP MM/PP ECC6.0 EhP6, MRP run can perform source determination provided the following is setup ?
(more than one answers)
A) Contract exist for the Material.
B) Source List with MRP relevant indicator.
C) Regular Vendor activation in the customizing.
D) Source List activate at the Plant parameter.
E) Purchasing Info Record is active for the material.
.
(more than one answers)
A) Contract exist for the Material.
B) Source List with MRP relevant indicator.
C) Regular Vendor activation in the customizing.
D) Source List activate at the Plant parameter.
E) Purchasing Info Record is active for the material.
.
Answer: B, E
ReplyDeleteThe Purchasing Info Record for the material must be active when including the source for the material in the source list with the MRP Relevancy indicator and therefore answer was B and E.