Question no 2876 : Maintenance Order Technical Completion

In SAP PM ECC6.0 EhP6, Maintenance Order at 'TECO' status, ___________________ .

(more than one answers)

A)   The Settlement Rule cannot be changed.
B)   The linked Notification cannot be 'Put in Process' again unless Maintenance Order is reversed from TECO.
C)   Overhead Calculation can proceed.
D)   Balance costs in Maintenance Order after 'TECO', then Business Closing is Possible.
E)   Goods receipt for non-stock purchase order is not longer possible.
.

2 comments:

  1. At TECO:
    . Settlement rule can be changed.
    . Overhead Calculation can be done.
    . Goods movement no longer possible.
    . Invoice for Non-Stock or External Operations are possible with variance written back to MO.
    . Balance must be ZERO better CLSD.