In SAP Plant Maintenance as at ECC6.0 EhP6, which of the following are per-requisites for Maintenance Order Settlement ?
(only one answer)
A) Order must be Released.
B) Order must have 'TECO' status.
C) All Goods Issues are completed.
D) All Operations Confirmation must have been done.
E) All Purchase Requisitions must have been converted to Purchase Orders.
.
(only one answer)
A) Order must be Released.
B) Order must have 'TECO' status.
C) All Goods Issues are completed.
D) All Operations Confirmation must have been done.
E) All Purchase Requisitions must have been converted to Purchase Orders.
.
Answer: A
ReplyDeleteAs long as Order is Released (not locked nor deletion flag) and before CLSD (business closing), settlement is possible. SAP does not check goods movement or confirmation completeness when performing settlement process (as at ECC6.0 EhP6) standard SAP delivery.