Question no 2863 : MRP generated planned orders

In SAP MM as at ECC6.0 EhP6, what kind of planned orders characteristics can be generated from an MRP run ?

(more than one answers)

A)   Planned Order with a Supplying Plant.
B)   Planned Order assigned to a Contract.
C)   Planned Order assigned to a Scheduling Agreement.
D)   Planned Order with a Production Version.
E)   Planned Order with a Vendor.
.

1 comment:

  1. Source Determination in MM can get you A, B, C, E (but for MRP it has to work with a Source List as well)
    Quota Arrangement activated for MRP can get you all the choices mentioned.