In SAP MM as at ECC6.0 EhP6, what kind of planned orders characteristics can be generated from an MRP run ?
(more than one answers)
A) Planned Order with a Supplying Plant.
B) Planned Order assigned to a Contract.
C) Planned Order assigned to a Scheduling Agreement.
D) Planned Order with a Production Version.
E) Planned Order with a Vendor.
.
(more than one answers)
A) Planned Order with a Supplying Plant.
B) Planned Order assigned to a Contract.
C) Planned Order assigned to a Scheduling Agreement.
D) Planned Order with a Production Version.
E) Planned Order with a Vendor.
.
Source Determination in MM can get you A, B, C, E (but for MRP it has to work with a Source List as well)
ReplyDeleteQuota Arrangement activated for MRP can get you all the choices mentioned.