In SAP MM IM, which of the following can be changed in the Material Document item details ?
(more than one answer)
A) Unloading Point.
B) Entering a new Message Output.
C) Attachments.
D) Document Item Text.
E) Goods Recipient.
.
(more than one answer)
A) Unloading Point.
B) Entering a new Message Output.
C) Attachments.
D) Document Item Text.
E) Goods Recipient.
.
Answer: A, B, D, E
ReplyDeleteFor Goods Receipt with ref. to PO. (MB02)
ReplyDelete. Unloading Point
. Document Item Text
For Goods Issue to Cost Center (MB02)
. Goods Recipient
. Document Item Text
In MB02, Message Output is accessible for each Item, you can add new message output but I have not been able to change the existing per-determined message output's destination. (As at ECC6.0 EhP5)
As at ECC6.0 EhP5, there are no Attachments possible in MB02 but attachments can be done in MB03 or when displaying the material document in MIGO. In addition, when displaying material document via MIGO, you can also select to print plus 'print version' option (if it was not printed yet).
As at ECC6.0 EhP5, when in MIGO you can only display the material document like MB03. But, it seems there are no 'ACTIVITY' selection for changing material document like MB02; and therefore, those changes that can be done via MB02 is yet to be possible within MIGO. (unless I miss a config somewhere in IMG)