In SAP MM or PP MRP, which of the following you cannot perform in MD05 (MRP List) ?

(only one answer)

A)   You can manually delete the MRP List.
B)   You can confirm a Planned Order.
C)   You can delete a Planned Order.
D)   You can convert a Planned Order to a Production Order.
E)   You can copy simulated firmed Planned Orders from LTP.
.

2 comments:

  1. You can only copy simulated firmed planned order from LTP to the operative environment (ie: S/R list) in MD43