In SAP MM Inventory Management, when changing a manually creates reservation (that was not yet processed) using MB22, whichmof the following is not possible ?

(more than one answers)

A)    Change the Account Assignment data.
B)    Change the Material number.
C)    Change the Plant.
D)    Change the Date.
E)    Change thr Quantity.
.

2 comments:

  1. (You CAN perform the following Changes)
    change general item data (for example, storage location, batch, recipient)
    change the requirement date for one item or for all items
    change the quantity of a reservation item if you need more or less than the quantity reserved until now
    set or reset various indicators (final issue indicator, Movement allowed indicator)
    check the availability of the material for the base date specified
    delete items
    enter new items

    (You CANNOT do the following Changes)
    You cannot change the account assignment data (for example, cost center or order). If the account assignment is incorrect, you must delete the reservation and enter a new reservation.
    You cannot change the material number or the plant for an item. If either of these entries is incorrect, you must delete the item and enter a new item.