Question no 2628 : QM for External Processing in PP

In SAP QM for PP, which of the following Inspection type is suitable for Control Key PP02 where the External Process Purchase Order when Goods Receipt will generate an Inspection Lot for inspecting the works done by the external vendor for the Production Operation ?

(only one answer)

A)    Inspection type 01
B)    Inspection type 0130
C)    Inspection type 02
D)    Inspection type 03
E)    Inspection type 0310
.

2 comments:

  1. Inspection type 01 for Goods Receipt from PO
    Inspection type 02 for Goods Issue
    Inspection type 03 for In-Process Quality for Production