In SAP MM, which of the following data view is absolutely necessary for creating a Purchasing Document ?
(only one answer)
A) Purchasing data view.
B) MRP data view.
C) Plant/Storage data view.
D) Accounting data view.
E) Purchasing Text data view.
.
(only one answer)
A) Purchasing data view.
B) MRP data view.
C) Plant/Storage data view.
D) Accounting data view.
E) Purchasing Text data view.
.
Answer: A
ReplyDeleteYou could probably be laughing when you see such a question on the real SAP certification and there is no doubt for a Single Answer question that Purchasing data view is the answer.
ReplyDeleteBut, why is Accounting data view not necessary?
For consumable scenario, there are no Stocks Account Posting therfore no Stock Account determination is necessary via the Valuation Class from the Accounting view. In case a Material was created without the Accounting data view, at Purchasing the system respond is for you to enter an Account Assingment key.
And, why isn't the Plant/Storage data viee a requirement?
There is a customizing in IMG-MM-IM-GR-Create Storage Location Automatically for the Plant. If this is set, it is not necessary to create the Plant/Storage view as it will be created automatically at GR.