In SAP PP as at ECC6.0 EhP6, the "Read PP Master Data" function can be used in which of the following situations without ERROR ?

(more than one answers)

A)   Possibly when there are no goods movement yet.
B)   Only before Release Production orders.
C)   Production order can be Released but Shop Papers not printed yet.
D)   Provided Availability check has not been executed at either CRTD or REL status.
E)   Possibly when confirmations not entered yet.
.

1 comment:

  1. Both CRTD and REL status allows "Read PP Master Data" however they must not be any goods movement or confirmations.