In SAP PP as at ECC6.0 EhP6, which of the following time segments directly affects capacity requirement / capacity load calculations ?
(more than one answers)
A) Setup times.
B) Transport time.
C) Move time.
D) Operation Control key.
E) In-house Production time (Material Master).
.
(more than one answers)
A) Setup times.
B) Transport time.
C) Move time.
D) Operation Control key.
E) In-house Production time (Material Master).
.
Answer: A, D
ReplyDeleteA) Setup time, processing time, tear-down time all affects capacity loads calculations as the machine is reserved when this activities are done.
ReplyDeleteB, C) Transport time/Move time, Wait time, Queue times all are inter-operation times which affects scheduling not not used in Capacity load.
ReplyDeleteD) Operation control key have parameter setting that can switch off capacity requirement calculation.
ReplyDeleteE) In-House Production times are used when no Routing is desirable either at Basic Dates or Lead-time scheduling (when no Routing is found) at MRP run.