Question no 3138 : Time segments for Capacity Load

In SAP PP as at ECC6.0 EhP6, which of the following time segments directly affects capacity requirement / capacity load calculations ? 

(more than one answers)

A)   Setup times.
B)   Transport time.
C)   Move time.
D)   Operation Control key.
E)   In-house Production time (Material Master).
.

5 comments:

  1. A) Setup time, processing time, tear-down time all affects capacity loads calculations as the machine is reserved when this activities are done.

    ReplyDelete
  2. B, C) Transport time/Move time, Wait time, Queue times all are inter-operation times which affects scheduling not not used in Capacity load.

    ReplyDelete
  3. D) Operation control key have parameter setting that can switch off capacity requirement calculation.

    ReplyDelete
  4. E) In-House Production times are used when no Routing is desirable either at Basic Dates or Lead-time scheduling (when no Routing is found) at MRP run.

    ReplyDelete