In SAP PP as at ECC6.0 EhP6, which of the following features can be defined using the MRP Strategy ?
(more than one answers)
A) Ignore Stocks in Planning (Gross Planning).
B) Sales Order consumption to Planned Independent Requirement.
C) Transfer of Sales Order to MD04 to MRP calculations.
D) Planned Independent Requirement considerations.
E) Safety stock as Opening Stocks.
.
(more than one answers)
A) Ignore Stocks in Planning (Gross Planning).
B) Sales Order consumption to Planned Independent Requirement.
C) Transfer of Sales Order to MD04 to MRP calculations.
D) Planned Independent Requirement considerations.
E) Safety stock as Opening Stocks.
.
E) Control of Safety Stocks in MRP Strategy not yet available as at ECC6.0 EhP6.