In SAP PP as at ECC6.0 EhP6, the configuration for Reduction Strategies assigned to Operations Scheduling allows one to define Reduction Measures for which of the following time elements EXCEPT one ?
(only one answer)
A) Queue time reduction.
B) Reduction by splitting.
C) Reduction by overlapping.
D) Move time reduction.
E) Goods Receipt Processing time reduction.
.
(only one answer)
A) Queue time reduction.
B) Reduction by splitting.
C) Reduction by overlapping.
D) Move time reduction.
E) Goods Receipt Processing time reduction.
.
Answer: E
ReplyDeleteYou define the reduction strategies in Customizing at the IMG path for "Shop Floor Control" by choosing Operations - Scheduling - Define Reduction Strategies.
ReplyDelete