Question no 3157 : Interopration Times

In SAP PP as at ECC6.0 EhP6, which of the following are elements of Inter-operation time when scheduling a Production Order ?

(more than one answers)

A)   Good Receipt processing time.
B)   Move time.
C)   Wait time.
D)   Release period.
E)   Opening period.
.

1 comment:

  1. Generally Move time, Wait time, and Queue times are considered Inter-operation times. Some documentations claim that Float before Production and Float after Production are also inter-operations times.