In SAP PP as at ECC6.0 EhP6, which of the following are elements of Inter-operation time when scheduling a Production Order ?
(more than one answers)
A) Good Receipt processing time.
B) Move time.
C) Wait time.
D) Release period.
E) Opening period.
.
(more than one answers)
A) Good Receipt processing time.
B) Move time.
C) Wait time.
D) Release period.
E) Opening period.
.
Generally Move time, Wait time, and Queue times are considered Inter-operation times. Some documentations claim that Float before Production and Float after Production are also inter-operations times.