Question no 3147 : Sequence of MRP Mechanics

In SAP PP as at ECC6.0 EhP6, which of the following is the correct sequence of MRP mechanics in the SAP MRP planning run ?

1.   Lot sizing
2.   Gross to net calculation
3.   BOM explosion
4.   Procurement
5.   Scheduling

(only one answers)

A)    1, 2, 3, 4, 5
B)    2, 3, 4, 5, 1
C)    2, 1, 4, 3, 5
D)    2, 1, 4, 5, 3
E)    1, 2, 4, 5, 3
.

1 comment:

  1. step 1: Gross to Net requirement (to determine to Qty)
    step 2: Lot sizing rule application (to determine the Final Qty)
    step 3: Procurement (to decide internal/external and special procurement)
    step 4: Scheduling (to calculate Start and Finish dates)
    step 5: BOM Explosion (if applicable)

    ReplyDelete