In SAP PP as at ECC6.0 EhP6, which of the following is the correct sequence of MRP mechanics in the SAP MRP planning run ?
1. Lot sizing
2. Gross to net calculation
3. BOM explosion
4. Procurement
5. Scheduling
(only one answers)
A) 1, 2, 3, 4, 5
B) 2, 3, 4, 5, 1
C) 2, 1, 4, 3, 5
D) 2, 1, 4, 5, 3
E) 1, 2, 4, 5, 3
.
1. Lot sizing
2. Gross to net calculation
3. BOM explosion
4. Procurement
5. Scheduling
(only one answers)
A) 1, 2, 3, 4, 5
B) 2, 3, 4, 5, 1
C) 2, 1, 4, 3, 5
D) 2, 1, 4, 5, 3
E) 1, 2, 4, 5, 3
.
step 1: Gross to Net requirement (to determine to Qty)
ReplyDeletestep 2: Lot sizing rule application (to determine the Final Qty)
step 3: Procurement (to decide internal/external and special procurement)
step 4: Scheduling (to calculate Start and Finish dates)
step 5: BOM Explosion (if applicable)