In SAP PPDI and PPPI as at ECC6.0 EhP6, Engineering Change Notice can be applied to the following objects EXCEPT ?
(only one answer)
A) Material Master.
B) Work Center or Resources.
C) Bills of Material.
D) Routing.
E) Recipe.
.
(only one answer)
A) Material Master.
B) Work Center or Resources.
C) Bills of Material.
D) Routing.
E) Recipe.
.
Not work center nor Resources.