In SAP PP LTP (Long Term Planning) as at ECC6.0 EhP6, which of the following control parameters can be set in the Long Term Planning Scenarios ?
(more than one answers)
A) Opening Stocks.
B) Firmed Receipts.
C) Switch off Direct Production.
D) Switch Consumption-Based Material to Dependent Requirements.
E) Routing Group and Counter.
.
(more than one answers)
A) Opening Stocks.
B) Firmed Receipts.
C) Switch off Direct Production.
D) Switch Consumption-Based Material to Dependent Requirements.
E) Routing Group and Counter.
.
Answer: A, B, C, D
ReplyDeleteReview the parameters allowed for LTP planning scenario in MS31.
ReplyDelete