In SAP as at ECC6.0 EhP6, Work Center or Resources can used for which of the following assignments for scheduling purpose ?

(more than one answers)

A)   Maintenance Task List.
B)   Service Entry Sheet.
C)   Routing.
D)   Rate Routing.
E)   Recipe.
.

2 comments:

  1. Work Center master in different modules are similar in design.
    It can be assigned to the following:
    . Standard Routing (for PPDI Production Orders)
    . Rate Routing (for PPDI Repetitive)
    . Recipe (for PPPI) but it is called Resources
    . Network operations (PS)
    . Maintenance Task List (PM/CS)
    . Inspection Plan (QM)