This Blog is mainly on SAP Exam Questions and Selected "How-to" SAP processes

Monday, May 2, 2016

Question no 3159 : Manufacturing Strategy

In SAP PP as at ECC6.0 EhP6, which of the following is a suitable strategy for case below ?

"A company make-to-order for customers, however, the lead time is very short for the Sales Order arrival, the Sales department has always able to secure forecast data from the customers and it has decided that planning can be based on forecast so that the raw material can be purchased to produce the necessary sub-assemblies in stock before the make-to-order sales order arrives from the customers".

(only one answer)

A)   Strategy 11.
B)   Strategy 20.
C)   Strategy 30.
D)   Strategy 50.
E)   Strategy 82.
.

2 comments:

  1. Strategy allows PIR for planning. However, MRP run for the FG creating planned orders with order type "VP" which cannot be converted production orders. However, BOM explosion will occur at MRP run to plan and execute for the raw material procurement and sub-assembly preparation. When the Sales Order arrive for the FG, MRP run will convert the planned order type from "VP" to "KD", this will allow conversion of these make-to-order planned order to make-to-order production orders.

    ReplyDelete

Note: Only a member of this blog may post a comment.