In SAP MM and PP for MRP area as at ECC6.0 EhP6, select those control parameters can can be set the MRP area for a Material Master ?
(more than one answers)
A) MRP Strategy.
B) Special Procurement type.
C) Lot Size key.
D) Procurement type.
E) Production version.
.
(more than one answers)
A) MRP Strategy.
B) Special Procurement type.
C) Lot Size key.
D) Procurement type.
E) Production version.
.
Answer: B, C
ReplyDeleteA, E) MRP3 and MRP4 data view data structures are not in the MRP area as at ECC6.0 EhP6
ReplyDeleteB, D) Procurement type (internal, external, or both) can only be set in the MRP 2 view and not the MRP area view. However, Special procurement key is allowed in both.
ReplyDeleteC) Not all Parameters in MRP1 and MPR2 view at the Plant level can be found in the MRP area but for example Lot size key can be found in both.
ReplyDelete