In SAP MM as at ECC6.0 EhP6, a Plant may not be required in which of the following Purchaaing Document ?
(more than one answers)
A) Purchasing Requisition.
B) RFQ.
C) Purchase Order.
D) Contract,
E) Scheduling Agreement.
.
(more than one answers)
A) Purchasing Requisition.
B) RFQ.
C) Purchase Order.
D) Contract,
E) Scheduling Agreement.
.
Answer: B, D
ReplyDeleteB) RFQ for negotiating a price for all plants hence resulting in PIR without Plant is possible.
ReplyDeleteD) Central contract without Plant is possible.